Quantities for slabs, footings, walls and piers — with your planned order, truck count and a planned truck arrival timeline. Runs in your browser. No login.

How to read this tool

  • CALCULATED Math from your entries.
  • USER INPUT Your numbers and assumptions.
  • VERIFY SPEC Confirm with your supplier, plans and project requirements.
  • ESTIMATE Planning aid only — not a dispatch schedule.
1 What are you pouring?
2 Dimensions USER INPUT
3 Order allowances

Your allowance. Example values are conveniences, not recommendations.

Extra volume you choose to carry, e.g. for pump line or hopper.

Supplier batch increment VERIFY SPEC

The order is rounded up to this step. Default 0.25 CY — confirm what your supplier batches.

Default 10.0 CY is a starting point only. Verify load size and legal load limits with your supplier.

Results

Enter dimensions to see quantities.

4 Planned truck arrival timeline ESTIMATE

Assumes one active placement point (one pump or chute). Arrival interval and unload time are separate: if trucks arrive faster than they unload, they wait; if slower, the placement point sits idle between loads.

The timeline appears once the order and trucks are calculated.

5 Pre-pour coordination reminders

Verify per plans, specifications and project requirements. This is a coordination reminder, not an inspection certification.

6 Copy field summary

For text, email, Fieldwire, Procore or a daily report. Only what you entered and what was calculated is included — nothing else is added.